The new water main project started in November 2021. With the pilot hole drilled using a Vermeer D24X40, a reaming pass was made and the bore hole was ready to receive the 6-inch pipe selected for the water line. To begin the pullback process, an initial 20-foot length of pipe was attached to the puller head and drill stem. As the driller began pulling the pipe in, the contractor utilized the cartridge style assembly method to join the Certa-Lok one stick at a time as the drilling continued. This process continued for the entire project length of 10,995 feet using multiple drill shots with a maximum drill length of 2500 feet. The upgrade to the water main system included installing the 6-inch fire protection line beside the existing 2-inch and 4-inch lines. A fire protection line is a dedicated pipe that carries a large volume of water specifically for firefighting; the line is installed in specific locations and connected to fire hydrants providing a reliable source of water with water volume and pressure guaranteed. The contractor seamlessly upgraded the existing water system by incorporating a 6-inch fire line integrated with the pre-existing infrastructure through a series of valves and connections. With the utility company monitoring the project, they noticed how efficiently the fire line was being installed and expanded the project to install more fire protection lines down other roads outside of the original plan. To handle the expanded project scope, the contractor skillfully processed several change orders, allowing installation and connection of more 6-inch pipes than originally planned.
Typically, a fire protection line is designed with a larger diameter pipe, compared to the drinking water distribution pipes, to handle higher water flow rates. The pipes are connected or ‘looped’ through a series of valves and control points allowing the fire department to isolate the fire protection line. The looped configuration of the pipe ensures a constant water pressure and flow even in the event of high water demand.
Certa-Lok C900 RJIB, manufactured by Westlake Pipe & Fittings, was well suited for the installation method selected by Evans Contracting. Certa-Lok joints can be assembled in less than 1 minute per joint and the cartridge-style assembly engages each joint as the pipe is in motion working seamlessly with pipe pullback operations; the pipe is ready to go into service immediately and can be installed by pulling or pushing the pipe. The cartridge-style assembly also offers a contained assembly area allowing the contractor to maintain the flow of traffic, with some residents not being aware that construction was taking place. The complete pipe length was successfully pulled in each of the project construction zones.
“It was very nice to see the project with thousands of feet of new water line being installed and most places the only visible work was a new fire hydrant,” said Cecil Jernigan, engineer at Fabre, a Bowman Company.
Originally specified for a traditional open cut method, the owner, engineer, and contractor saw the cost savings by installing the long sections of pipe by HDD instead of open cut. HDD minimizes surface disruption and eliminates the need for excavation, reducing the amount of time, cost, and resources required for site excavation.
“There were no issues with the product,” said Keith Chavis, construction manager at Evans Contracting Inc. “There was no concern pulling the pipe to the maximum drill length of 2500 feet, no issues at all.” Chavis further explained, “Construction time was also decreased and we were able to install the runs in fewer hours with less equipment than traditional open-cut technologies”.
With the success of the project, Midway Water System has asked Evans Contracting to continue improving fire protection systems in other surrounding roadways with the installation of another 6000-8000 feet of Certa-Lok water main via HDD.