Total Boring Solutions, subcontracted by SW Waterworks, used a Ditch Witch JT28 rig throughout. The project began with successful HDD installation of the 20-in. steel casing under N. Douglas Avenue: first pull (608 LF) from just west of N. Klein Avenue to N. Western Avenue; second pull (600 LF) from just west of N. Klein Avenue to N. Douglas Avenue.
Each bore followed the same sequence:
- Pilot bore
- 12-in. reamer pass
- Final 24-in. reamer pass to ensure generous annular space
A Certa-Lok® pull-head (using the identical spline-locking restraint) was attached to the lead joint, followed by a swivel that prevented pipe rotation while the reamer was turned by the rig. Additional four-joint segments were assembled during pullback as the pipe was pulled into the borehole. Peak pull force reached only 5,800 LBF—less than 10% of the 60,000 LBF safe-maximum pull-force capability of 12-in. DR14 Certa-Lok RJIB. The low forces confirmed excellent borehole geometry and minimal frictional drag. After completing the final HDD section, Certa-Lok was used as carrier pipe through the previously installed casing. Thanks to Certa-Lok’s substantially smaller bell outside diameter versus traditional bell harness restrained C900, the pipe easily slid into the 20-in. casing with ample clearance and was joined using standard spline-locked joints.
Final tie-ins at N. Western Avenue and N. Douglas Avenue required only small pavement patches. Despite sandy soil complications that delayed the casing and first bore, the entire project, casing, two long HDD pulls, and connections, was completed in just under one month.
“We had no problems with the pipe—it worked really well,” said Jackson Matthews, COO of SW Waterworks. “Without the early soil issues, we would have finished in two weeks.”
This project is one of several large-scale Certa-Lok HDD installations SW Waterworks has successfully completed in the Oklahoma City area, with additional projects already in the pipeline.