Initial actions focused on the open-cut installation along 6th Street, progressing west along Bay Road from the intersection. Trenchless methods, including jack and bore inside casing pipe, were employed for crossings like the Platte River, railroads, Four Mile Creek, Highway 75, and near Treasure Island Road on Buccaneer Boulevard. Traffic control, including alternating one-way lanes and temporary signals, minimized disruptions in suburban areas.
Westlake Pipe’s Certa-Lok restrained-joint PVC pipe emerged as the pivotal solution, used for approximately 39,000 LF total, including:
- 960 ft of 8-in. DR18 Certa-Lok RJIB
- 140 LF of 16-in. DR18 Certa-Lok RJIB
- 5,480 LF of 20-in. DR18 Certa-Lok RJIB
- 360 LF of 16-in. DR14 Certa-Lok coupled RJ
- C900 IB PVC segments – 100 LF 6-in. DR18, 2,300 LF 8-in. DR18, 29,060 LF 20-in. DR18, and 500 LF 16-in. DR14
The Certa-Lok spline-locked joints assembled in minutes, enabling dramatically faster installation than traditional gasketed C900 or fused HDPE. The spline-lock achieves a strong, secure, 100% restrained, service-ready joint that can withstand axial thrust, soil movement, and pressure surges in the unstable sandy conditions.
“Certa-Lok decreases time. Fusing requires time for heating up and cooling down—about 1.5 hours for fusing, compared to less than 10 minutes to install each stick of Certa-Lok,” said Jeff Grady, vice president, Valley Corp. “Certa-Lok gave us considerable time savings. Fusing requires a long ways to string pipe and increases rigging constraints.”
The higher stiffness of PVC maintained grade during backfill and compaction, eliminating joint disengagement risks, while its corrosion-free inherent properties provide a service life in excess of 100-years; superior to DI's vulnerability to rust or HDPE's flow limitations. Innovations included cartridge-style pullback for trenchless segments and co-location in easements to reduce environmental impact.
By December 5, 2025, crews had completed open cut along 6th Street and Bay Road, trenchless along Bay Road and Buccaneer Boulevard, and site prep at the South Platte Plant for winter. “Certa-Lok made this project go smooth and easy with only taking 2-3 minutes per pipe,” said John Mahon, superintendent, Valley Corp.
The outcome delivered on-time progress, zero joint leaks, full restraint in challenging soils, and safe, Omaha-quality water ensuring uninterrupted supply resilient to future floods.